White Pigeon Compressor Station
Project Description:
Location:
Owner:
Customer:
Duration:
Year of Completion:
Contract Value:
Project Scope Details:
.
.
Electrical Installation Highlights:
Location:
Owner:
Customer:
Duration:
Year of Completion:
Contract Value:
Project Scope Details:
.
.
Electrical Installation Highlights:
White Pigeon Compressor Station
White Pigeon, MI
Consumers Energy
Henkles & McCoy
15 Months
2010
Between $1 – $5 Million
New Construction for Compressor Station. The installation included, but was not limited to: Primary Electrical Service, Electrical Substation, Associated Instrumentation, Security System, Lighting, Compressor Building, Motor Control Station Building, Office Building, etc.
Over 700 Instruments, Panels, & Control Stations Installed
Over 50,000 Feet of Conduit & Tray Installed
Over 300,000 Feet of Wire Pulled
Over 3,000 Feet of EHT Tape Installed
White Pigeon, MI
Consumers Energy
Henkles & McCoy
15 Months
2010
Between $1 – $5 Million
New Construction for Compressor Station. The installation included, but was not limited to: Primary Electrical Service, Electrical Substation, Associated Instrumentation, Security System, Lighting, Compressor Building, Motor Control Station Building, Office Building, etc.
Over 700 Instruments, Panels, & Control Stations Installed
Over 50,000 Feet of Conduit & Tray Installed
Over 300,000 Feet of Wire Pulled
Over 3,000 Feet of EHT Tape Installed