Project Description:
Location: 
Owner:
Customer: 
Duration:
Year of Completion:
Contract Value:
Project Scope Details: 
.
.
Electrical Installation Highlights:

Athens Gas Compressor Station
Athens, MI
Vector Pipeline
Henkles & McCoy
6 Months
2009
Between $1 – $5 Million
New Construction for Compressor Station. The installation included, but was not limited to: Primary Electrical Service, Electrical Substation, Associated Instrumentation, Security System, Lighting, Compressor Building, Motor Control Station Building, Office Building, etc.
Over 150 Instruments, Panels, & Control Stations Installed
Over 25,000 Feet of Conduit & Tray Installed
Over 70,000 Feet of Wire Pulled
Over 500 Feet of EHT Tape Installed

 

 

 

Project Description:
Location: 
Owner:
Customer: 
Duration:
Year of Completion:
Contract Value:
Project Scope Details: 

 

Electrical Installation Highlights: 

Willow Gas Compressor Station
Ypsilanti, MI
Michigan Consolidated Gas
WJ O’Neil
6 Months
2009
Between $1 – $5 Million
Willow Gas Compressor Station
Over 200 Instruments, Panels, & Control Stations Installed
Over 40,000 Feet of Conduit & Tray Installed
Over 240,000 Feet of Wire Pulled
Over 300 Feet of EHT Tape Installed